The Township’s 2022 Annual Milling and Resurfacing Contract has been awarded to A. Liberoni, Inc. in the amount of $937,978.42. Work is anticipated to begin on or about Thursday, August 18, 2022 with an expected duration of about 4 to 5 weeks.
The roads included in this year’s program include:
Bellview Drive
Parkway Drive
McCallen Street
Hilltop Park road
Brookville Road (preparation work for synthetic fiber seal coat)
Southside Road (preparation work for synthetic fiber seal coat)
Pace Street
Westmoreland Avenue
Glass Street
Hamilton Road
Kelso Drive
Hunters Wood Lane
School Street
Pine Street
Pine Street Extension
Grape Street
Northeast Drive
Crestview Drive
Water Street
Haywood Road (preparation work for synthetic fiber seal coat)
Crown Road
Post Street
Sarah Court
Steven Drive
Terrace Drive
Hiland Place
Virginia Avenue
Old Jacks Run Road